Projects

Publicly reported projects in water transmission, desalination, wastewater, oil and gas, power and construction where FRP, GRP or GRE products are used or could be used. Where a source does not name the pipe or product material, the record says so.

Projects · 54 records
ProjectRecentNews / secondary source

New Water Pipeline to Feed Riyadh City 2: WTCO cancels Package B and Packages C1/C3 (~USD 556m) — pipe material not stated by source

Saudi ArabiaWaterWater transmission pipeline19 Nov 2026

MEED reports that the Water Transmission Company cancelled the tenders for two packages of the Riyadh City 2 transmission scheme, a roughly 136 km, 64–100 inch pipeline masterplan with large steel storage tanks.

FRP relevance: medium
Potential productsLarge-diameter GRP pipe (potential FRP application — not confirmed by source) — potential FRP application, not confirmed by source
Owner
Water Transmission Company (WTCO)
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Riyadh, Saudi Arabia
Project value
556 million (combined, cancelled packages)
Currency
USD
Status
Cancelled
Announced
19 Nov 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 19 Nov 2026 · Collected 21 Nov 2026 · Verified 21 Nov 2026Read original →
ProjectRecentNews / secondary source

Al-Hayah water pipeline (15 km) at Wadi Hali Dam, Mecca Province: bids invited — pipe material not stated by source

Saudi ArabiaWaterWater transmission pipeline17 Nov 2026

MEED reports that Saudi Arabia has invited bids for about 15 km of water transmission pipelines linked to Wadi Hali Dam; owner and deadline are behind the paywall.

FRP relevance: medium
Potential productsGRP pipe (potential FRP application — not confirmed by source) — potential FRP application, not confirmed by source
Owner
Not publicly confirmed
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Wadi Hali Dam, Mecca Province, Saudi Arabia
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Tender
Announced
17 Nov 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 17 Nov 2026 · Collected 21 Nov 2026 · Verified 21 Nov 2026Read original →
ProjectRecentNews / secondary source

Yanbu 300 MLD SWRO plant, Saudi Arabia: SWA cancels USD 272m WABAG award — pipe material not stated by source

Saudi ArabiaWaterDesalination14 Nov 2026

Saudi Water Authority cancelled the Yanbu seawater RO contract awarded to WABAG in July 2025, citing internal reasons; WABAG says the contract was never counter-signed. The scheme may be re-tendered, which could reopen pipe and tank packages.

FRP relevance: medium
Potential productsGRP/GRE intake, outfall and process piping · FRP tanks — potential FRP application, not confirmed by source
Owner
Saudi Water Authority (SWA)
Consultant
Not publicly confirmed
EPC / contractor
VA Tech Wabag (award cancelled)
Location
Yanbu, Red Sea coast, Saudi Arabia
Project value
272 million
Currency
USD
Status
Cancelled
Announced
14 Nov 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: SaudiGulf Projects · Published 14 Nov 2026 · Collected 16 Nov 2026 · Verified 16 Nov 2026Read original →
ProjectRecentNews / secondary source

ADNOC 48-inch West–East crude pipeline: Borouge to supply Borcoat PE coating for steel pipe

UAEOil & GasPipelines, Pipe coating10 Nov 2026

Borouge and NMDC signed at ADIPEC 2026 to supply Borcoat polyethylene coating for steel pipe on ADNOC's Jebel Dhanna–Fujairah line, expected to operate in 2027.

FRP relevance: low
Owner
ADNOC
Consultant
Not publicly confirmed
EPC / contractor
NMDC
Location
Jebel Dhanna to Port of Fujairah, UAE
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Under construction
Announced
10 Nov 2026
Expected completion
2027
Source type
News / secondary source
Source: SaudiGulf Projects · Published 10 Nov 2026 · Collected 14 Nov 2026 · Verified 14 Nov 2026Read original →
ProjectRecentNews / secondary source

Montoir-de-Bretagne LNG terminal renewal (Ulysse): Amiblu to supply and install DN1200 GRP overhead pipes

FranceOil & GasGRP pipe10 Nov 2026

Amiblu Pipes Spain won a turnkey scope to engineer, make and install two DN1200 GRP overhead lines (about 1.2 km in total) on a 6 m rack feeding two new open-rack vaporizers at Elengy's LNG terminal in France. Works are scheduled from March 2027 to January 2028 within a project budget reported at €220 million.

FRP relevance: high
Confirmed by sourceGRP pipe DN1200 (overhead seawater lines to ORV units)
Owner
Elengy
Consultant
Sacyr Proyecta (developer of overall renovation project, per source)
EPC / contractor
Amiblu Pipes Spain (GRP pipe turnkey scope)
Location
Montoir-de-Bretagne, France
Project value
220 million (overall project budget)
Currency
EUR
Status
Awarded
Announced
10 Nov 2026
Expected completion
2028-01
Source type
News / secondary source
Source: iAgua · Published 10 Nov 2026 · Collected 26 Nov 2026 · Verified 26 Nov 2026Read original →
ProjectRecentNews / secondary source

Al Hamriyah SWRO IWP (410,000 m³/d), Sharjah: Veolia wins pretreatment and remineralisation design package — pipe material not stated by source

UAEWaterDesalination6 Nov 2026

Veolia secured the design and technology package (DAF, dual-media filtration, limestone remineralisation) for ACWA Power's Al Hamriyah seawater RO plant, a deal worth nearly EUR 200m combined with an Oman O&M contract. SEWA separately says full 410,000 m³/d output is now expected in Q4 2028.

FRP relevance: medium
Potential productsGRP/FRP process piping, filter vessels and chemical tanks (potential) — potential FRP application, not confirmed by source
Owner
Sharjah Electricity, Water and Gas Authority (SEWA) — offtaker; ACWA Power — developer
Consultant
Not publicly confirmed
EPC / contractor
ACWA Power (developer); Veolia (design and technology, pretreatment/remineralisation)
Location
Al Hamriyah, Sharjah, UAE
Project value
Nearly EUR 200m (Veolia, combined with Al Asilah O&M contract)
Currency
EUR
Status
Awarded
Announced
5 Nov 2026
Expected completion
About 272,000 m³/d by Q2 2027; full 410,000 m³/d expected Q4 2028 (SEWA)
Source type
News / secondary source
Source: Smart Water Magazine · Published 6 Nov 2026 · Collected 8 Nov 2026 · Verified 8 Nov 2026Read original →
ProjectRecentNews / secondary source

Haliba field produced-water treatment facilities, Abu Dhabi: Al Dhafra Petroleum awards USD 272m DBO deal to Excel ASTRA — pipe material not stated by source

UAEOil & GasProduced water treatment6 Nov 2026

Al Dhafra Petroleum signed a design-build-operate agreement worth about AED 1bn with Excel ASTRA Engineering & Construction for produced-water treatment facilities at its Haliba field. The deal was signed at ADIPEC 2026; capacity and duration were not disclosed.

FRP relevance: medium
Potential productsGRE/GRP produced-water piping and FRP tanks (potential) — potential FRP application, not confirmed by source
Owner
Al Dhafra Petroleum
Consultant
Not publicly confirmed
EPC / contractor
Excel ASTRA Engineering & Construction LLC
Location
Haliba field, Abu Dhabi, UAE
Project value
AED 1 billion (about USD 272m)
Currency
AED
Status
Awarded
Announced
6 Nov 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: SaudiGulf Projects · Published 6 Nov 2026 · Collected 9 Nov 2026 · Verified 9 Nov 2026Read original →
ProjectRecentNews / secondary source

Aramco East-West crude pipeline expansion (Abqaiq–Yanbu) — pipe material not stated by source

Saudi ArabiaOil & GasPipelines5 Nov 2026

Aramco says work has started on expanding its ~1,200 km, 7 million b/d East-West crude line; Saudi officials target up to 10 million b/d of pipeline export capacity.

FRP relevance: low
Potential productsGRE/FRP piping for ancillary utilities — potential FRP application, not confirmed by source
Owner
Saudi Aramco
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Abqaiq to Yanbu, Saudi Arabia
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Announced
Announced
5 Nov 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 5 Nov 2026 · Collected 14 Nov 2026 · Verified 14 Nov 2026Read original →
ProjectRecentNews / secondary source

Saudi Irrigation Organisation tenders dam rehabilitation and irrigation transmission lines in Asir — pipe material not stated by source

Saudi ArabiaWaterGRP pipe, FRP tanks5 Nov 2026

Five tenders cover Ghaleba, Ahmar and Al-Darham dams, supply and transmission lines and a Khamis Mushait–Dalghan line, with bids due between 10 and 29 November; six prequalifications cover Al-Baha and Jizan irrigation schemes with pumping stations, tanks and transmission lines. Pipe and tank materials are not stated.

FRP relevance: medium
Potential productsGRP transmission pipe · FRP/GRP storage tanks — potential FRP application, not confirmed by source
Owner
Saudi Irrigation Organisation
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Asir region; Al-Baha and Jizan (prequalifications), Saudi Arabia
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Tender
Announced
5 Nov 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 5 Nov 2026 · Collected 10 Nov 2026 · Verified 10 Nov 2026Read original →
ProjectRecentIndustry / company source

Veolia wins ~EUR 200m in desalination contracts: Al Hamriyah (UAE) design and Al Asilah (Oman) O&M — pipe material not stated

UAE, OmanWaterDesalination5 Nov 2026

Veolia secured a design contract for the 410,000 m³/day Al Hamriyah desalination plant in the UAE and a five-year operations and optimisation contract for the 80,000 m³/day Al Asilah plant in Oman. The source gives no piping or materials details.

FRP relevance: medium
Potential productsGRP intake/outfall and process piping · FRP tanks — potential FRP application, not confirmed by source
Owner
Not publicly confirmed
Consultant
Not publicly confirmed
EPC / contractor
Veolia
Location
Al Hamriyah, UAE; Al Asilah, Oman
Project value
Nearly 200 million (two contracts combined)
Currency
EUR
Status
Awarded
Announced
5 Nov 2026
Expected completion
Not publicly confirmed
Source type
Industry / company source
Source: Water Online (Veolia release) · Published 5 Nov 2026 · Collected 27 Nov 2026 · Verified 27 Nov 2026Read original →
ProjectRecentNews / secondary source

North Kabd wastewater treatment plant (up to 1m m³/d), Kuwait: CSCEC breaks ground on KWD 998m DBO project — pipe material not stated by source

KuwaitWaterWastewater treatment4 Nov 2026

CSCEC held the groundbreaking for Kuwait's North Kabd wastewater treatment plant and related works for the Ministry of Public Works, a design-build-operate-maintain contract of about KWD 998m signed in July 2026. Capacity is stated at up to 1 million m³/day.

FRP relevance: medium
Potential productsGRP sewer/effluent pipes, FRP tanks, covers and odour-control ducting (potential) — potential FRP application, not confirmed by source
Owner
Ministry of Public Works, Kuwait
Consultant
Not publicly confirmed
EPC / contractor
China State Construction Engineering Corporation (CSCEC)
Location
North Kabd, Kuwait
Project value
About KWD 998m (about USD 3.3bn)
Currency
KWD
Status
Under construction
Announced
4 Nov 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: SaudiGulf Projects · Published 4 Nov 2026 · Collected 9 Nov 2026 · Verified 9 Nov 2026Read original →
ProjectRecentNews / secondary source

NWC LTOM12 (North Western B Cluster), Saudi Arabia: Al-Yamama reported winner for seven STPs — pipe material not stated by source

Saudi ArabiaWaterFRP pipe, FRP tanks30 Oct 2026

National Water Company has reportedly selected local firm Al-Yamama for package 12 of its long-term O&M sewage programme, covering construction and upgrade of seven sewage treatment plants totalling about 162,000 m³/d, at a reported tariff of SR0.98/m³.

FRP relevance: medium
Potential productsGRP/FRP process piping, tanks and covers at STPs — potential, not confirmed — potential FRP application, not confirmed by source
Owner
National Water Company (NWC)
Consultant
Not publicly confirmed
EPC / contractor
Al-Yamama
Location
North Western B Cluster, Saudi Arabia
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Awarded
Announced
30 Oct 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 30 Oct 2026 · Collected 12 Nov 2026 · Verified 12 Nov 2026Read original →
ProjectArchiveNews / secondary source

Hassyan SWRO IWP (≈272,000 m³/d), Dubai: ACWA signs 30-year water purchase agreement with DEWA — pipe material not stated by source

UAEWaterDesalination28 Oct 2026

ACWA disclosed a SAR 1.79bn (USD 478m) WPA with DEWA for a further Hassyan seawater RO independent water project of about 272,000 m³/d; ACWA holds 40% and financial impact is expected from 2030. Intake, outfall and transmission materials are not stated.

FRP relevance: medium
Potential productsGRP/GRE intake, outfall and process piping · FRP tanks — potential FRP application, not confirmed by source
Owner
DEWA
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Hassyan Complex, Dubai
Project value
1,790,000,000
Currency
SAR
Status
Awarded
Announced
28 Oct 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: Zawya (via TradingView) · Published 28 Oct 2026 · Collected 31 Oct 2026 · Verified 2 Nov 2026Read original →
ProjectArchiveNews / secondary source

Dubai Tasreef stormwater programme phase 3: four contracts worth AED 3bn awarded — pipe material not stated by source

UAEWaterGRP pipe26 Oct 2026

Dubai Municipality awarded four contracts under phase 3 of its Tasreef programme to build or extend about 100 km of main stormwater lines with pipes up to 3 m in diameter. The source does not state the pipe material or the value of each package.

FRP relevance: medium
Potential productsLarge-diameter GRP stormwater pipe (up to DN3000) · GRP manholes and fittings — potential FRP application, not confirmed by source
Owner
Dubai Municipality
Consultant
Not publicly confirmed
EPC / contractor
ARIFCO Group, CSCEC Middle East, DETech Contracting, Nael Construction & Contracting (as reported via Construction Business News ME; package split not published)
Location
Jumeirah, Umm Suqeim, Al Marmoom, Al Wasl Road, Sheikh Zayed Rd–Al Khail Rd, Dubai
Project value
3,000,000,000
Currency
AED
Status
Awarded
Announced
25 Oct 2026
Expected completion
Programme phased completion by 2033
Source type
News / secondary source
Source: Smart Water Magazine · Published 26 Oct 2026 · Collected 27 Oct 2026 · Verified 27 Oct 2026Read original →
ProjectArchiveNews / secondary source

Egypt clears Suez (1m m³/d) and Port Said (900,000 m³/d) desalination plants and four industrial wastewater plants for PPP tender — pipe material not stated by source

EgyptWaterGRP pipe, FRP tanks26 Oct 2026

Egypt's Higher Committee for PPP Affairs approved tendering two large seawater desalination plants in Suez and Port Said plus four industrial wastewater plants as public-private partnerships. Values and pipe or tank materials were not disclosed.

FRP relevance: medium
Potential productsGRP intake/outfall and transmission pipe · FRP chemical tanks — potential FRP application, not confirmed by source
Owner
Government of Egypt (Higher Committee for PPP Affairs; Ministry of Housing, Utilities and Urban Communities)
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Suez, Port Said, Ismailia; industrial plants at Amreya, Abu Rawash, Wadi El Natrun, El Raswa
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Upcoming
Announced
25 Oct 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: Smart Water Magazine · Published 26 Oct 2026 · Collected 27 Oct 2026 · Verified 27 Oct 2026Read original →
ProjectArchiveNews / secondary source

NEOM Green Hydrogen Co.: RFQ for interim 14,530 m³/d wastewater treatment plant at Oxagon — pipe/tank material not stated by source

Saudi ArabiaWaterWastewater24 Oct 2026

NGHC sought qualifications for an EPC interim wastewater plant with biocide removal, storage tanks, a pumping station and pipelines, targeted to be ready by mid-April 2027. The RFQ submission date was 22 November 2026.

FRP relevance: medium
Potential productsFRP tanks / GRP process piping (potential FRP application — not confirmed by source) — potential FRP application, not confirmed by source
Owner
NEOM Green Hydrogen Company (NGHC)
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Oxagon Industrial Quarter, NEOM, Saudi Arabia
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Tender
Announced
24 Oct 2026
Expected completion
2027-04-15 (target readiness per source)
Source type
News / secondary source
Source: MEED · Published 24 Oct 2026 · Collected 28 Nov 2026 · Verified 28 Nov 2026Read original →
ProjectArchiveNews / secondary source

Sharjah Hamriyah wastewater treatment plant EPC — pipe and tank materials not stated by source

UAEWater21 Oct 2026

CWT (Clean Water Treatment) and BHT Environ say their consortium was selected for the EPC of a wastewater treatment plant in Sharjah's Hamriyah region. Owner, capacity, value and schedule were not disclosed.

FRP relevance: medium
Potential productsGRP pipe · FRP tanks · FRP grating — potential FRP application, not confirmed by source
Owner
Not publicly confirmed
Consultant
Not publicly confirmed
EPC / contractor
CWT (Clean Water Treatment) / BHT Environ consortium
Location
Hamriyah, Sharjah, UAE
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Awarded
Announced
21 Oct 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: SaudiGulf Projects · Published 21 Oct 2026 · Collected 22 Oct 2026 · Verified 22 Oct 2026Read original →
ProjectArchiveNews / secondary source

Mirfa–Liwa water transmission and distribution scheme, Abu Dhabi: Taqa issues DBO RFP — pipe material not stated by source

UAEWaterWater transmission pipeline, Storage tanks20 Oct 2026

Taqa Transmission and Taqa Distribution have issued an RFP, reportedly on a design-build-operate basis, for a Mirfa pumping station, about 125 km of transmission lines to Muzairah with branches to Madinat Zayed and Liwa, storage tanks and four distribution clusters. MEED reports bids are now due 5 January 2027 after an extension.

FRP relevance: medium
Potential productsGRP pipe · GRE pipe · FRP tanks — potential FRP application, not confirmed by source
Owner
Taqa Transmission / Taqa Distribution
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Mirfa, Madinat Zayed and Liwa, Abu Dhabi, UAE
Project value
775 million (original estimate)
Currency
USD
Status
Tender
Announced
20 Oct 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 20 Oct 2026 · Collected 22 Nov 2026 · Verified 22 Nov 2026Read original →
ProjectArchiveNews / secondary source

Al Asilah SWRO plant (80,000 m³/d), Oman: Bahwan Veolia Water wins five-year O&M contract — materials not stated by source

OmanWaterDesalination16 Oct 2026

The Veolia–Bahwan Engineering joint venture will operate and maintain the solar-supported Al Asilah desalination plant in South Al Sharqiyah for five years. It is Veolia's fourth major desalination plant in Oman; no contract value or pipe material was disclosed.

FRP relevance: low
Potential productsGRP pipe · FRP tanks — potential FRP application, not confirmed by source
Owner
Al Asilah Operation and Maintenance LLC (awarding entity); plant owned by Al Asilah Desalination Company
Consultant
Not publicly confirmed
EPC / contractor
Bahwan Veolia Water (O&M)
Location
Al Asilah, South Al Sharqiyah, Oman
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Awarded
Announced
16 Oct 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: Smart Water Magazine · Published 16 Oct 2026 · Collected 17 Oct 2026 · Verified 24 Oct 2026Read original →
ProjectArchiveNews / secondary source

KOC tenders 24-inch gas export pipeline in southeast Kuwait — pipe material not stated by source

KuwaitOil & GasPipeline13 Oct 2026

Kuwait Oil Company has tendered a 24-inch gas export line from Booster Station 171 to the Intermediate Slug Catcher via TP-1, with the contractor supplying valves, piping and fittings. Bids are due in early January 2027.

FRP relevance: low
Potential productsComposite/GRE piping for ancillary services (potential FRP application — not confirmed by source) — potential FRP application, not confirmed by source
Owner
Kuwait Oil Company (KOC)
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Southeastern Kuwait
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Tender
Announced
13 Oct 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 13 Oct 2026 · Collected 28 Nov 2026 · Verified 28 Nov 2026Read original →
ProjectArchiveNews / secondary source

NWC LTOM16, Saudi Arabia: tender for rehabilitation of 14 sewage treatment plants (153,000 m³/d) — pipe material not stated by source

Saudi ArabiaWaterFRP pipe, FRP tanks7 Oct 2026

NWC has tendered package 16 of its long-term O&M programme to rehabilitate and upgrade 14 STPs with 153,000 m³/d design capacity; bids are due 3 May 2027. The same report says the LTOM14 Eastern A Cluster deadline moved to 30 November.

FRP relevance: medium
Potential productsGRP/FRP piping, tanks, covers and gratings for STP rehabilitation — potential, not confirmed — potential FRP application, not confirmed by source
Owner
National Water Company (NWC)
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Saudi Arabia (region not stated)
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Tender
Announced
7 Oct 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 7 Oct 2026 · Collected 12 Nov 2026 · Verified 12 Nov 2026Read original →
ProjectArchiveIndustry / company source

Riyadh East ISTP (200,000–400,000 m³/d): five consortia bid — pipe material not stated by source

Saudi ArabiaWaterGRP pipe, FRP tanks29 Sept 2026

Sharakat received five bids for the 25-year BOOT Riyadh East sewage plant, which includes a treated-effluent transmission pipeline for irrigation. Commercial operation targeted for 2030.

FRP relevance: medium
Potential productsPotential GRP pipe for TSE transmission line · Potential FRP tanks/covers — potential FRP application, not confirmed by source
Owner
Sharakat (Saudi Water Partnership Company)
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Riyadh, Saudi Arabia
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Tender
Announced
29 Sept 2026
Expected completion
2030 (target COD)
Source type
Industry / company source
Source: Smart Water Magazine (Sharakat release) · Published 29 Sept 2026 · Collected 13 Oct 2026 · Verified 13 Oct 2026Read original →
ProjectArchiveNews / secondary source

Sitra IWPP, Bahrain — award expected Q4 2026 (pipe material not stated by source)

BahrainWaterGRP pipe15 Sept 2026

Bahrain's Electricity and Water Authority is evaluating TAQA and ACWA Power for the Sitra independent water and power project, with award expected in Q4 2026.

FRP relevance: medium
Potential productsGRP intake/outfall and process pipe · FRP tanks — potential FRP application, not confirmed by source
Owner
Electricity and Water Authority (EWA), Bahrain
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Sitra, Bahrain
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Tender
Announced
15 Sept 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: Zawya Projects · Published 15 Sept 2026 · Collected 12 Oct 2026 · Verified 12 Oct 2026Read original →
ProjectArchiveOfficial source

National Grid Electricity Distribution plans framework for GRP substation enclosures (UK)

UKPowerGRP enclosures8 Sept 2026

NGED published a planned-procurement notice covering prefabricated GRP enclosures, roofs and doors for 11kV/6.6kV secondary substations (Lot 1), alongside anti-vandal steel enclosures (Lot 2). No closing date or value has been published yet.

FRP relevance: high
Confirmed by sourceGRP substation enclosures · GRP roofs and doors
Owner
National Grid Electricity Distribution PLC
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
UK distribution network
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Upcoming
Announced
8 Sept 2026
Expected completion
Not publicly confirmed
Source type
Official source
Source: Find a Tender (UK) · Published 8 Sept 2026 · Collected 17 Nov 2026 · Verified 17 Nov 2026Read original →
ProjectArchiveNews / secondary source

NWC Northern Cluster: 15-year rehab and O&M of nine sewage plants awarded — materials not stated by source

Saudi ArabiaWaterFRP tanks, GRP pipe, FRP grating2 Sept 2026

NWC signed Armada and Zhangzhou United Waters for a SAR 1.3 bn+ contract to rehabilitate and operate nine STPs (337,000+ m³/d) in Qassim, Hail, Al-Jouf and Northern Borders.

FRP relevance: medium
Potential productsPotential FRP covers, gratings, tanks and GRP pipe in plant rehabilitation — potential FRP application, not confirmed by source
Owner
National Water Company (NWC)
Consultant
Not publicly confirmed
EPC / contractor
Armada / Zhangzhou United Waters
Location
Unaizah, Al-Bukairiyah, Al-Muznib, Al-Ras, Hail, Baqa'a, Sakaka, Turaif
Project value
1,300,000,000+
Currency
SAR
Status
Awarded
Announced
2 Sept 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: Smart Water Magazine · Published 2 Sept 2026 · Collected 13 Oct 2026 · Verified 13 Oct 2026Read original →
ProjectArchiveNews / secondary source

Kuwait Doha SWRO Stage II (60 MIGD): WABAG–HEISCO JV signs USD 371.5 m DBO contract — pipe material not stated by source

KuwaitWaterDesalination25 Aug 2026

Kuwait's MEWRE contracted a VA Tech WABAG-led JV with HEISCO to design, build and operate a 60 MIGD seawater RO plant with recarbonation and partial solar supply; 36-month build plus five years O&M.

FRP relevance: medium
Potential productsGRP/GRE intake, brine and process piping · FRP tanks — potential FRP application, not confirmed by source
Owner
Ministry of Electricity, Water & Renewable Energy (MEWRE), Kuwait
Consultant
Not publicly confirmed
EPC / contractor
VA Tech WABAG – HEISCO JV
Location
Doha, Kuwait
Project value
114.28 million KWD (about 371.5 million USD)
Currency
KWD
Status
Awarded
Announced
1 Jun 2026
Expected completion
36 months construction + 5 years O&M
Source type
News / secondary source
Source: SaudiGulf Projects · Published 25 Aug 2026 · Collected 14 Oct 2026 · Verified 14 Oct 2026Read original →
ProjectArchiveNews / secondary source

DEWA GRE water transmission pipeline EPC contract (various Dubai locations)

UAEWaterGRE pipe18 Aug 2026

DEWA has received three bids for an EPC contract to build glass-reinforced epoxy water transmission pipelines and related works across Dubai; award was expected in Q3 2026.

FRP relevance: high
Confirmed by sourceGRE water transmission pipelines
Potential productsGRE fittings
Owner
Dubai Electricity and Water Authority (DEWA)
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Various locations, Dubai
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Tender
Announced
18 Aug 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: Zawya Projects · Published 18 Aug 2026 · Collected 12 Oct 2026 · Verified 12 Oct 2026Read original →
ProjectArchiveNews / secondary source

Network Rail FLOW programme for standard GRP modular footbridge components (est. GBP 15.4m)

UKConstructionGRP structures, Pultrusion6 Aug 2026

Network Rail ran pre-market engagement for GRP structural systems and modular bridge components for roughly 10–15 standard footbridges, with an indicative value of GBP 15.4m. The engagement window closed in September 2026; a formal tender has not yet been listed.

FRP relevance: high
Confirmed by sourceGRP modular footbridge components
Owner
Network Rail Infrastructure Limited
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
UK rail network
Project value
15400000
Currency
GBP
Status
Upcoming
Announced
6 Aug 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: Stotles (Find a Tender 074596-2026) · Published 6 Aug 2026 · Collected 17 Nov 2026 · Verified 17 Nov 2026Read original →
ProjectArchiveNews / secondary source

DEWA GRE Water Transmission Pipelines Project 3: seven bids, Green Oasis lowest at AED 608m

UAEWaterGRE pipe4 Aug 2026

Seven contractors bid for DEWA's GRE transmission pipeline Project 3 in Dubai; Green Oasis General Contracting was lowest, with bids ranging up to about AED 858m. No award reported.

FRP relevance: high
Confirmed by sourceGRE water transmission pipelines
Potential productsGRE fittings
Owner
Dubai Electricity and Water Authority (DEWA)
Consultant
Not publicly confirmed
EPC / contractor
Green Oasis General Contracting (lowest bidder, award pending)
Location
Emirate of Dubai
Project value
AED 608.08m (lowest bid)
Currency
AED
Status
Tender
Announced
4 Aug 2026
Expected completion
24 months from award (per IndexBox)
Source type
News / secondary source
Source: SaudiGulf Projects · Published 4 Aug 2026 · Collected 19 Oct 2026 · Verified 15 Nov 2026Read original →
ProjectArchiveNews / secondary source

Hassyan SWRO Phase 2 GRE pipelines, Project 2: three bids, Tristar lowest at AED 792.6m

UAEWaterGRE pipe22 Jul 2026

DEWA received three offers for the second GRE water transmission pipeline package serving Hassyan SWRO phase two. Tristar Engineering & Construction bid lowest; Green Oasis and Wade Adams followed. No award reported.

FRP relevance: high
Confirmed by sourceGRE water transmission pipelines
Potential productsGRE fittings
Owner
Dubai Electricity and Water Authority (DEWA)
Consultant
Not publicly confirmed
EPC / contractor
Tristar Engineering & Construction (lowest bidder, award pending)
Location
Hassyan, Dubai
Project value
AED 792.59m (lowest bid); AED 800.02m; AED 989.65m
Currency
AED
Status
Tender
Announced
22 Jul 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 22 Jul 2026 · Collected 26 Oct 2026 · Verified 26 Oct 2026Read original →
ProjectArchiveNews / secondary source

Oman Nama Cluster 1 water and wastewater O&M: Suez-led consortium wins USD 2.28bn 15-year contract — pipe material not stated

OmanWaterWater networks, Wastewater30 Jun 2026

The performance-based deal covers Muscat and both Sharqiyah governorates, including about 10,700 km of water pipelines, 22 wastewater plants and some 3,000 km of sewers.

FRP relevance: low
Potential productsGRP pipe repair and replacement · FRP tanks — potential FRP application, not confirmed by source
Owner
Nama Water Services
Consultant
Not publicly confirmed
EPC / contractor
Suez-led consortium (National Sustainable Water Alliance)
Location
Muscat, North and South Sharqiyah, Oman
Project value
2,280,000,000
Currency
USD
Status
Awarded
Announced
30 Jun 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 30 Jun 2026 · Collected 14 Nov 2026 · Verified 14 Nov 2026Read original →
ProjectArchiveNews / secondary source

Qatar: USD 104m sewer works and terminal pumping station contract — pipe material not stated by source

QatarWaterGRP pipe26 Jun 2026

A local contractor won a contract covering remaining sewer works across 27,320 hectares plus the first phase of a new terminal pumping station; owner and contractor names were behind MEED's paywall.

FRP relevance: medium
Potential productsGRP sewer pipe · FRP manholes — potential FRP application, not confirmed by source
Owner
Not publicly confirmed
Consultant
Not publicly confirmed
EPC / contractor
Local firm (name not stated in visible text)
Location
Qatar
Project value
104 million
Currency
USD
Status
Awarded
Announced
26 Jun 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 26 Jun 2026 · Collected 7 Nov 2026 · Verified 7 Nov 2026Read original →
ProjectArchiveNews / secondary source

Sur water transmission upgrade, Oman: Al-Jesr United wins ~USD 80m contract — new pipeline material not stated

OmanWaterWater transmission3 Jun 2026

Nama Water Services awarded the EPC for upgrading the Sur DP pump station and building about 17 km of new transmission pipeline; MEED says facility pipes and fittings will be ductile iron but does not name the new line's material. Works were due to start in Q3 2026 and last about two years.

FRP relevance: medium
Potential productsFRP pipe — potential FRP application, not confirmed by source
Owner
Nama Water Services
Consultant
Ibn Khaldun Almadaen Engineering Consultants
EPC / contractor
Al-Jesr United
Location
Sur, Oman
Project value
80000000
Currency
USD
Status
Awarded
Announced
3 Jun 2026
Expected completion
About two years from a Q3 2026 start
Source type
News / secondary source
Source: MEED · Published 3 Jun 2026 · Collected 17 Nov 2026 · Verified 17 Nov 2026Read original →
ProjectArchiveNews / secondary source

Fujairah I IWP: USD 286 m EPC contract awarded — pipe material not stated by source

UAEWaterGRP pipe, FRP tanks5 May 2026

EtihadWE awarded a USD 286 million EPC contract to an Emirati-Spanish JV for its second PPP desalination project, Fujairah I IWP. Capacity not visible in the source.

FRP relevance: medium
Potential productsPotential GRP intake/outfall and process piping — potential FRP application, not confirmed by source
Owner
Etihad Water and Electricity (EtihadWE)
Consultant
Not publicly confirmed
EPC / contractor
Emirati-Spanish joint venture (not named in visible text)
Location
Fujairah, UAE
Project value
286,000,000
Currency
USD
Status
Awarded
Announced
5 May 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: Zawya Projects · Published 5 May 2026 · Collected 13 Oct 2026 · Verified 13 Oct 2026Read original →
ProjectArchiveNews / secondary source

Al Jardaa–Mihlah (Sawt) water transmission network, Oman: Hassan Allam Construction awarded — pipe material not stated by source

OmanWaterWater transmission pipeline9 Mar 2026

Oman Water & Wastewater Services Company awarded Hassan Allam Construction a scheme in Al Sharqiyah North covering about 76 km of transmission pipelines, roughly 600 km of distribution networks, seven reservoirs, two pumping stations and seven solar-powered systems.

FRP relevance: medium
Potential productsGRP/GRE transmission pipe · FRP tanks — potential FRP application, not confirmed by source
Owner
Oman Water & Wastewater Services Company
Consultant
Not publicly confirmed
EPC / contractor
Hassan Allam Construction
Location
Al Jardaa to Mihlah (Sawt), Al Sharqiyah North Governorate, Oman
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Awarded
Announced
9 Mar 2026
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: Smart Water Magazine · Published 9 Mar 2026 · Collected 23 Nov 2026 · Verified 23 Nov 2026Read original →
ProjectArchiveIndustry / company source

Eccles WwTW stormwater storage shaft (United Utilities AMP8): Amiblu supplies Hobas DN2000 GRP pipes

UKWaterGRP pipe, FRP fittings26 Feb 2026

Amiblu is supplying Hobas DN2000 pipes and fittings, including an elbow and end cap, to J Murphy for the upgraded stormwater storage shaft at Eccles wastewater works. A later phase is planned to add a 60,000 m³ storage tank.

FRP relevance: high
Confirmed by sourceHobas GRP pipes DN2000 · GRP fittings (DN2000 elbow, end cap)
Owner
United Utilities
Consultant
Not publicly confirmed
EPC / contractor
J Murphy Ltd
Location
Eccles, Greater Manchester, UK
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Under construction
Announced
26 Feb 2026
Expected completion
Not publicly confirmed
Source type
Industry / company source
Source: Amiblu · Published 26 Feb 2026 · Collected 13 Nov 2026 · Verified 13 Nov 2026Read original →
ProjectArchiveNews / secondary source

Northern Jeddah sewer networks: Civil Works Company wins two NWC contracts (USD 143m) — pipe material not stated by source

Saudi ArabiaWaterSewer pipe19 Feb 2026

NWC awarded two sewer contracts covering roughly 133 km of 200–1,500 mm pipelines plus sewage tunnels in six northern Jeddah districts, with 32 months for works; pipe material is not stated.

FRP relevance: medium
Potential productsGRP pipe · FRP manholes — potential FRP application, not confirmed by source
Owner
National Water Company (NWC)
Consultant
Not publicly confirmed
EPC / contractor
Civil Works Company
Location
Northern Jeddah (Al-Bashair, Al-Asala, Al-Falah, Taybah, Abhar Al-Shamaliyah, Al-Hamdaniyah), Saudi Arabia
Project value
536.3 million
Currency
SAR
Status
Awarded
Announced
19 Feb 2026
Expected completion
32 months from site handover
Source type
News / secondary source
Source: MEED · Published 19 Feb 2026 · Collected 18 Nov 2026 · Verified 18 Nov 2026Read original →
ProjectArchiveNews / secondary source

Riyadh–Qassim water transmission pipeline — pipe material not stated by source

Saudi ArabiaWaterLarge-diameter pipe13 Feb 2026

Vision Invest was named preferred bidder for the 859 km Riyadh–Qassim transmission line; Sharakat expects financial close in 2026.

FRP relevance: medium
Potential productsGRP/GRE transmission pipe — potential FRP application, not confirmed by source
Owner
Sharakat (formerly SWPC)
Consultant
Not publicly confirmed
EPC / contractor
Vision Invest (preferred bidder)
Location
Riyadh – Al Qassim
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Announced
Announced
Not publicly confirmed
Expected completion
Financial close expected 2026
Source type
News / secondary source
Source: MEED · Published 13 Feb 2026 · Collected 11 Oct 2026 · Verified 11 Oct 2026Read original →
ProjectArchiveNews / secondary source

DEWA awards AED 216m GRE water transmission pipeline contract (7.1 km main line, 20 interconnections)

UAEWaterGRE pipe18 Dec 2025

DEWA awarded a contract to supply, install and commission GRE pipelines of various diameters, including a 7.1 km main transmission line and 20 network interconnections, with completion due within 24 months. Contractor not named in the source.

FRP relevance: high
Confirmed by sourceGRE water transmission pipelines
Potential productsGRE fittings
Owner
Dubai Electricity and Water Authority (DEWA)
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Multiple locations, Dubai
Project value
216 million
Currency
AED
Status
Awarded
Announced
18 Dec 2025
Expected completion
Within 24 months of award
Source type
News / secondary source
Source: Zawya Projects · Published 18 Dec 2025 · Collected 19 Oct 2026 · Verified 19 Oct 2026Read original →
ProjectDate unverifiedNews / secondary source

Mataf FRP ceiling panels, Masjid al-Haram

Saudi Arabia, UAEConstructionArchitectural FRP1 Dec 2025

PCT built more than 25,000 FRP panels in Dubai for the Mataf ceiling in Mecca, with Sicomin supplying resin and gelcoat. Installation was slated to finish in Q4 2025, with further phases in development.

FRP relevance: high
Confirmed by sourceFRP architectural ceiling panels · gelcoat systems
Owner
Not stated
Consultant
Not publicly confirmed
EPC / contractor
PCT (fabricator)
Location
Makkah
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Completed
Announced
Not publicly confirmed
Expected completion
Q4 2025 (slated)
Source type
News / secondary source
Source: CompositesWorld · Published 1 Dec 2025 · Collected 11 Oct 2026 · Verified 11 Oct 2026Read original →
ProjectArchiveNews / secondary source

Hafar Al-Batin and Al-Qaisomah sewer network (184 km): NWC awards USD 59m contract — pipe material not stated by source

Saudi ArabiaWaterSewer pipe20 Nov 2025

NWC awarded a package covering about 184 km of sanitary sewer pipelines in Hafar Al-Batin and Al-Qaisomah; the visible article text does not give the pipe material.

FRP relevance: medium
Potential productsGRP pipe — potential FRP application, not confirmed by source
Owner
National Water Company (NWC)
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Hafar Al-Batin and Al-Qaisomah, Eastern Province, Saudi Arabia
Project value
59 million
Currency
USD
Status
Awarded
Announced
20 Nov 2025
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 20 Nov 2025 · Collected 18 Nov 2026 · Verified 18 Nov 2026Read original →
ProjectArchiveNews / secondary source

Jubail Industrial City 2 industrial wastewater plant: Marafiq–Veolia–Lamar consortium wins USD 500m contract — materials not stated

Saudi ArabiaWaterGRP pipe, FRP tanks16 Sept 2025

MEED reported a Marafiq, Veolia and Lamar Holding consortium won a SAR 1.875bn, 30-year concession for an industrial wastewater plant at Jubail Industrial City 2 treating effluent from Satorp's Amiral complex, including spent caustic. A February 2026 MEED report names Orascom Construction as EPC contractor. Materials are not stated.

FRP relevance: medium
Potential productsCorrosion-resistant GRP piping and FRP tanks for industrial effluent (potential) — potential FRP application, not confirmed by source
Owner
Not publicly confirmed
Consultant
Not publicly confirmed
EPC / contractor
Orascom Construction (EPC); developer: Marafiq / Veolia / Lamar Holding consortium
Location
Jubail Industrial City 2, Saudi Arabia
Project value
1875000000
Currency
SAR
Status
Awarded
Announced
16 Sept 2025
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 16 Sept 2025 · Collected 18 Oct 2026 · Verified 17 Nov 2026Read original →
ProjectArchiveNews / secondary source

Shuaibah SWRO phase 2 (545,000 m³/d): Al-Fatah Water & Power main contractor — pipe material not stated

Saudi ArabiaWaterGRP pipe, FRP tanks16 Sept 2025

MEED reported that construction of the USD 521m Shuaibah seawater reverse-osmosis phase 2 plant south of Jeddah began in June 2025 after Al-Fatah Water & Power was appointed main contractor. No pipe or tank materials are named.

FRP relevance: medium
Potential productsGRP intake/outfall and process piping (potential) · FRP tanks (potential) — potential FRP application, not confirmed by source
Owner
Not publicly confirmed
Consultant
Not publicly confirmed
EPC / contractor
Al-Fatah Water & Power
Location
Shuaibah, Red Sea coast south of Jeddah, Saudi Arabia
Project value
521000000
Currency
USD
Status
Under construction
Announced
16 Sept 2025
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 16 Sept 2025 · Collected 18 Oct 2026 · Verified 18 Oct 2026Read original →
ProjectArchiveNews / secondary source

Shuqaiq–Jizan water transmission system phase 4 — pipe material not stated by source

Saudi ArabiaWaterGRP pipe16 Sept 2025

MEED reported the roughly USD 3bn, 523 km, 600,000 m³/d transmission scheme procured by the Saudi water transmission company as under bid evaluation, with award expected by end-2025; it was first tendered in 2023. Pipe material is not stated.

FRP relevance: medium
Potential productsLarge-diameter GRP/GRE transmission pipe (potential) — potential FRP application, not confirmed by source
Owner
Water Transmission & Technologies Company (WTTCO)
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Al Shuqaiq to Jizan, Saudi Arabia
Project value
3000000000
Currency
USD
Status
Tender
Announced
16 Sept 2025
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 16 Sept 2025 · Collected 18 Oct 2026 · Verified 18 Oct 2026Read original →
ProjectArchiveNews / secondary source

Ghazlan 1 power plant expansion: Amiantit pipe supply — pipe type not stated by source

Saudi ArabiaPowerGRP pipe10 Sept 2025

Amiantit received a SAR 41.29 m award letter from China Energy Engineering's Zhejiang Thermal Power unit to supply pipes for Saudi Electricity's Ghazlan 1 expansion. The disclosure does not state the pipe material.

FRP relevance: medium
Potential productsGRP/GRE pipe (Amiantit product range) — potential FRP application, not confirmed by source
Owner
Saudi Electricity Co.
Consultant
Not publicly confirmed
EPC / contractor
China Energy Engineering Zhejiang Thermal Power Construction
Location
Ghazlan, Eastern Province
Project value
41.29 m incl. VAT
Currency
SAR
Status
Awarded
Announced
10 Sept 2025
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: Argaam · Published 10 Sept 2025 · Collected 11 Oct 2026 · Verified 11 Oct 2026Read original →
ProjectArchiveNews / secondary source

Riyadh Northern Ring water transmission system phase 1, package B: USD 146m award — pipe material not stated by source

Saudi ArabiaWaterGRP pipe8 Sept 2025

The Saudi Water Authority appointed Saudi Services for Electro Mechanic Works as main contractor for package B of the Riyadh Northern Ring transmission scheme, valued at about USD 146m within a USD 266m masterplan.

FRP relevance: medium
Potential productsLarge-diameter GRP/GRE transmission pipe — potential FRP application, not confirmed by source
Owner
Saudi Water Authority (SWA)
Consultant
Not publicly confirmed
EPC / contractor
Saudi Services for Electro Mechanic Works
Location
Riyadh, Saudi Arabia
Project value
146m
Currency
USD
Status
Awarded
Announced
8 Sept 2025
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: MEED · Published 8 Sept 2025 · Collected 15 Nov 2026 · Verified 15 Nov 2026Read original →
ProjectArchiveNews / secondary source

Jubail–Buraydah water transmission pipeline — 587 km carbon steel line (per MEED)

Saudi ArabiaWaterLarge-diameter pipe5 Mar 2025

A 587 km line linking the Eastern Province and Qassim with 650,000 m³/day capacity, two pumping stations and 11 reservoirs, under a 35-year BOOT agreement. MEED names Mutlaq Al-Ghowairi Contracting as EPC contractor and describes the main line as carbon steel; commercial operation has moved to Q2 2029.

FRP relevance: low
Potential productsTank internals / FRP fittings at reservoirs (potential) — potential FRP application, not confirmed by source
Owner
Saudi Water Partnership Company (now Sharakat)
Consultant
Not publicly confirmed
EPC / contractor
Al Jomaih Energy & Water / Nesma / Buhur consortium
Location
Jubail – Al Qassim
Project value
8.5 bn
Currency
SAR
Status
Under construction
Announced
5 Mar 2025
Expected completion
Q2 2029
Source type
News / secondary source
Source: Enterprise AM · Published 5 Mar 2025 · Collected 11 Oct 2026 · Verified 17 Nov 2026Read original →
ProjectArchiveIndustry / company source

Dubai well-field project: Future Pipe Industries to supply Wavistrong GRE pipelines for 520 wells

UAEWaterGRE pipe23 Jan 2025

FPI announced an award to supply Wavistrong glass-reinforced epoxy pipe for a Dubai well programme of 369 recovery wells, 108 dual-purpose wells and 43 monitoring wells, after the specification was switched from carbon steel to GRE. Client, consultant, value and pipe sizes are not named.

FRP relevance: high
Confirmed by sourceWavistrong GRE pipe
Owner
Not publicly confirmed
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Dubai, UAE
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Awarded
Announced
23 Jan 2025
Expected completion
Not publicly confirmed
Source type
Industry / company source
Source: Future Pipe Industries · Published 23 Jan 2025 · Collected 18 Oct 2026 · Verified 18 Oct 2026Read original →
ProjectDate unverifiedNews / secondary source

Ajman Sewage Biorefinery Plant Phase 3 (60 MLD): WABAG-led consortium wins contract — pipe material not stated by source

UAEWaterGRP pipePublication date not stated by source

WABAG leads a consortium contracted by Ajman Sewerage Company for the 60 MLD Phase 3 sewage biorefinery, with a 24-month contract period. Zawya reports the award alongside WABAG's Kuwait Doha SWRO win; contract value not disclosed.

FRP relevance: medium
Potential productsGRP/FRP pipe, tanks and gratings for wastewater treatment — potential FRP application, not confirmed by source
Owner
Ajman Sewerage (Private) Company Ltd
Consultant
Not publicly confirmed
EPC / contractor
WABAG-led consortium
Location
Ajman, UAE
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Awarded
Announced
Not publicly confirmed
Expected completion
24-month contract period
Source type
News / secondary source
Source: Zawya · Published: Publication date not stated by source · Collected 15 Nov 2026 · Verified 15 Nov 2026Read original →
ProjectDate unverifiedIndustry / company source

Albufeira seawater desalination plant uses Amiblu GRP intake and brine lines

PortugalWaterGRP pipeMarch 2026

Amiblu will supply GRP pipelines and fittings for seawater intake and brine return at a planned reverse-osmosis plant in Portugal's Algarve.

FRP relevance: high
Confirmed by sourceGRP intake and brine pipelines · GRP fittings
Owner
Not stated
Consultant
Not publicly confirmed
EPC / contractor
Amiblu (pipe supplier)
Location
Albufeira, Algarve
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Upcoming
Announced
Not publicly confirmed
Expected completion
Not publicly confirmed
Source type
Industry / company source
Source: Amiblu · Published: March 2026 · Collected 11 Oct 2026 · Verified 11 Oct 2026Read original →
ProjectDate unverifiedOfficial source

Briceni irrigation rehabilitation (Moldova) and Polish power plant GRP orders

Moldova, Poland, TürkiyeWaterGRP pipe2026 disclosure

A Turkish listed pipe maker disclosed EUR 5.74 m of export orders, led by GRP and HDPE pipe for a World Bank-financed irrigation project in Moldova plus GRP pipe for a power plant in Poland. Deliveries run through 2026.

FRP relevance: high
Confirmed by sourceGRP pipes
Owner
Not publicly confirmed
Consultant
Not publicly confirmed
EPC / contractor
Not publicly confirmed
Location
Briceni, Moldova; Poland
Project value
5.74 m
Currency
EUR
Status
Awarded
Announced
Not publicly confirmed
Expected completion
2026
Source type
Official source
Source: KAP (Public Disclosure Platform, Türkiye) · Published: 2026 disclosure · Collected 11 Oct 2026 · Verified 11 Oct 2026Read original →
ProjectDate unverifiedNews / secondary source

Hassyan SWRO Phase 2 GRE water transmission pipelines

UAEWaterGRE pipeBids received 2026

DEWA received bids from eight contractors to lay glass-reinforced epoxy transmission lines serving the 60 MIGD second phase of the Hassyan desalination plant. Binladin Contracting came in as lowest bidder; award follows DEWA's evaluation.

FRP relevance: high
Confirmed by sourceGRE water transmission pipelines
Potential productsGRE fittings · flanges
Owner
Dubai Electricity and Water Authority (DEWA)
Consultant
Not publicly confirmed
EPC / contractor
Binladin Contracting (lowest bidder, award pending)
Location
Hassyan, Dubai
Project value
AED 335.92m (lowest bid, Binladin); highest bid AED 495.20m
Currency
AED
Status
Tender
Announced
Not publicly confirmed
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: Zawya / TradeArabia · Published: Bids received 2026 · Collected 11 Oct 2026 · Verified 12 Oct 2026Read original →
ProjectDate unverifiedNews / secondary source

Ras Mohaisen–Baha–Makkah water transmission pipeline: 19 bidders prequalified — pipe material not stated by source

Saudi ArabiaWaterLarge-diameter pipeArticle undated

SWPC prequalified 19 developers and consortia for a 300 km pipeline of up to 400,000 m³/day, to be procured as a BOOT project. Fichtner is technical advisor.

FRP relevance: medium
Potential productsGRP/GRE transmission pipe — potential FRP application, not confirmed by source
Owner
SWPC (now Sharakat)
Consultant
Fichtner (technical), Synergy Consulting (financial)
EPC / contractor
Not publicly confirmed
Location
Ras Mohaisen – Al Baha – Makkah
Project value
Not publicly confirmed
Currency
Not publicly confirmed
Status
Tender
Announced
Not publicly confirmed
Expected completion
Not publicly confirmed
Source type
News / secondary source
Source: ME Construction News · Published: Article undated · Collected 11 Oct 2026 · Verified 11 Oct 2026Read original →
ProjectDate unverifiedNews / secondary source

Rayis–Rabigh water transmission pipeline — pipe material not stated by source

Saudi ArabiaWaterLarge-diameter pipeAward date not stated

Saudi Arabia's first water transmission PPP: a 150 km line carrying 500,000 m³/day toward Makkah and Madinah, awarded to an Alkhorayef-led consortium. Commercial operation was planned for Q2 2026.

FRP relevance: medium
Potential productsGRP/GRE transmission pipe — potential FRP application, not confirmed by source
Owner
SWPC (now Sharakat)
Consultant
Not publicly confirmed
EPC / contractor
Alkhorayef Water & Power Technologies-led consortium
Location
Rayis – Rabigh
Project value
2 bn (SAR 7.78 bn)
Currency
USD
Status
Under construction
Announced
Not publicly confirmed
Expected completion
Q2 2026 (planned)
Source type
News / secondary source
Source: Smart Water Magazine · Published: Award date not stated · Collected 11 Oct 2026 · Verified 11 Oct 2026Read original →