ProjectArchiveOfficial source
National Grid Electricity Distribution plans framework for GRP substation enclosures (UK)
NGED published a planned-procurement notice covering prefabricated GRP enclosures, roofs and doors for 11kV/6.6kV secondary substations (Lot 1), alongside anti-vandal steel enclosures (Lot 2). No closing date or value has been published yet.
FRP relevance: high
Confirmed by sourceGRP substation enclosures · GRP roofs and doors
- Owner
- National Grid Electricity Distribution PLC
- Consultant
- Not publicly confirmed
- EPC / contractor
- Not publicly confirmed
- Location
- UK distribution network
- Project value
- Not publicly confirmed
- Currency
- Not publicly confirmed
- Status
- Upcoming
- Announced
- 8 Sept 2026
- Expected completion
- Not publicly confirmed
- Source type
- Official source
Published 8 Sept 2026 · Collected 17 Nov 2026 · Last verified 17 Nov 2026
Original source
Find a Tender (UK) · Official source
Read the original at Find a Tender (UK) →This page is an original short summary. The full content belongs to its publisher.