ProjectArchiveNews / secondary source
DEWA awards AED 216m GRE water transmission pipeline contract (7.1 km main line, 20 interconnections)
DEWA awarded a contract to supply, install and commission GRE pipelines of various diameters, including a 7.1 km main transmission line and 20 network interconnections, with completion due within 24 months. Contractor not named in the source.
FRP relevance: high
Confirmed by sourceGRE water transmission pipelines
Potential productsGRE fittings
- Owner
- Dubai Electricity and Water Authority (DEWA)
- Consultant
- Not publicly confirmed
- EPC / contractor
- Not publicly confirmed
- Location
- Multiple locations, Dubai
- Project value
- 216 million
- Currency
- AED
- Status
- Awarded
- Announced
- 18 Dec 2025
- Expected completion
- Within 24 months of award
- Source type
- News / secondary source
Published 18 Dec 2025 · Collected 19 Oct 2026 · Last verified 19 Oct 2026
Original source
Zawya Projects · News / secondary source
Read the original at Zawya Projects →This page is an original short summary. The full content belongs to its publisher.