Hassyan SWRO Phase 2 GRE water transmission pipelines
DEWA received bids from eight contractors to lay glass-reinforced epoxy transmission lines serving the 60 MIGD second phase of the Hassyan desalination plant. Binladin Contracting came in as lowest bidder; award follows DEWA's evaluation.
FRP relevance: high
Confirmed by sourceGRE water transmission pipelines
Potential productsGRE fittings · flanges
- Owner
- Dubai Electricity and Water Authority (DEWA)
- Consultant
- Not publicly confirmed
- EPC / contractor
- Binladin Contracting (lowest bidder, award pending)
- Location
- Hassyan, Dubai
- Project value
- AED 335.92m (lowest bid, Binladin); highest bid AED 495.20m
- Currency
- AED
- Status
- Tender
- Announced
- Not publicly confirmed
- Expected completion
- Not publicly confirmed
- Source type
- News / secondary source
Published: Bids received 2026 · Collected 11 Oct 2026 · Last verified 12 Oct 2026
Original source
Zawya / TradeArabia · News / secondary source
Read the original at Zawya / TradeArabia →Also reported by: AGBI
This page is an original short summary. The full content belongs to its publisher.